Pacific Motorway Upgrade
Client: Queensland Department of Main Roads
Location: Queensland
Start: December 1997
Finish: November 1999
Contract Type: Construct only/Schedule of rates
Value: $130 million
Description:
The scope of work involved Leighton Contractors upgrading a 12-km section of the motorway from four to eight lanes. This is the longest section of the six packages of work that makes up the 42-km upgrade of the Pacific Motorway, which had a total value of around $500 million.
The contract included the construction of:
- 400,000 square metres of plain concrete pavement;
- four grade separated interchanges with bridges spanning the motorway;
- five other motorway bridges;
- three major culverts; and,
- eleven kilometres of service roads.