Kuala Lumpur - Putrajaya Highway

Client:  Maju Holdings Sdn Bhd
Location:  Malaysia
Start:  January 2005
Finish:  September 2007
Contract Type:  Design and construct
Value:  A$310 million (at 30 June 2007)
Description:  

Leighton International* was the lead contractor for the design & construct project to build a dedicated highway linking Kuala Lumpur to Putrajaya, the new regional centre south of Kuala Lumpur, which houses the new Malaysian Government Administration Complex.

The highway consists of approximately 26 kilometres of 2 and 3 lane dual carriageway, of which 10 kilometres is elevated and 16 kilometres is at grade. There are four major interchanges and two toll plazas along the length of the highway. The project has allowed for modern design protocol inclusive of toll system, lightings, variable message signs, landscaping and noise barriers.

*As of 30 June 2011 Leighton International’s activities were transferred to other Group companies. Leighton International project descriptions have been retained for historical purposes.